Bahrain’s Electricity and Water Authority (EWA) is expected to award the engineering, procurement, and construction (EPC) contract for a new seawater reverse osmosis (SWRO) desalination plant on Hawar Island in the first quarter of 2026, according to project sources.
Project Overview
- Initial Capacity: 1 million imperial gallons per day (MIGD)
- Future Expansion: Up to 3 MIGD in later phases
- Tender Details: Issued on October 1, 2025; bids due by November 30, 2025
- Planned Award Date: February 2026
- Completion Target: Q1 2028
Strategic Importance
The project is part of Bahrain’s long-term water security strategy, designed to meet growing demand and reduce reliance on imported water. It complements separate tenders for:
- Seawater intake and outfall systems
- Storage tanks
- Water transmission pumps
Next Steps
Once awarded, the EPC contractor will begin work on the first phase, with future expansions planned to triple capacity. The initiative underscores Bahrain’s commitment to sustainable water solutions amid regional climate challenges.
(Source: ZAWYA)